Fort Myers Riverfront: Legacy Harbour Marina and the Boardwalk

A land-use attorney representing Legacy Harbour Marina spoke at a City of Fort Myers design review meeting in late August. Citizen Portal reported that she said the city's new waterfront walkway concept raised "concerns regarding that drawbridge." She wasn't objecting to the idea of a public path along the Caloosahatchee. She was asking the design team to sit down with the people who just spent $15 million rebuilding a marina before finalizing a boardwalk that runs past their docks.

That detail adds context to this year's riverfront story. Legacy Harbour Marina is open again after nearly four years without a working marina at that address. A public plan for the sidewalk beside it is still being drawn, on a separate track from the marina's reopening.

What Actually Reopened This Year

Legacy Harbour Marina sits on 13 acres at 2044 West First Street, on the stretch of river most people picture when they think of downtown Fort Myers. Hurricane Ian destroyed the original facility in 2022. AIRN Management spent the years since rebuilding it from the pilings up, partnering with Bellingham Marine to install a Unifloat concrete dock system on 70-foot steel piles, the kind of infrastructure built to take the next storm better than the last one did. The rebuilt marina reopened this spring with 131 slips ranging from 40 to 150 feet. "This marina has long served as a homeport for boaters traveling Florida's west coast," AIRN CEO Rick Budd said when the reopening was announced, calling it a long-term commitment to the local boating community.

The other piece of news at that address is a restaurant, and it has its own history worth knowing. The building at 2024 West First Street was the Chart House starting in 1984. Joe's Crab Shack took over the space in 2003 and closed in 2025 when its lease ran out. Now restaurateur Leonard Lemmer is opening Nellie's Boatyard on the same site, with a late 2026 target. Lemmer already runs Cantina Laredo in Fort Myers and Walk-On's Sports Bistreaux in Cape Coral, and in July he bought the Nervous Nellie's property on Fort Myers Beach outright after leasing it for twelve years. Nellie's Boatyard will draw on that Fort Myers Beach menu, overlooking the same 131 slips that just came back online.

If you've walked past that building for the last few years and wondered what was going to happen to it, the marina and the restaurant answer both halves of the question at once. The water came back, and the plate is following.

Two Marinas With Almost the Same Story

Fort Myers actually has two marina projects moving at once along this river, and confusing them is easy to do. Legacy Harbour Marina is privately owned and just reopened. The Fort Myers Yacht Basin is a different property entirely, owned by the city and sitting west of the Edison Bridge in front of the Edison Grand Apartments. The city leased it to Suntex Marinas for 30 years starting in April 2022, months before Ian hit.

Suntex's original permit only covered repairing and replacing the existing docks. In June 2024, the company filed a much larger application, one that calls for filling part of the basin, dredging a new channel, and expanding the slip count to 286. That scope change triggered a multi-agency federal review, including an endangered species evaluation for the smalltooth sawfish and manatee populations that use the Caloosahatchee. As of the most recent public update this spring, that federal permit was still moving through review, with no construction schedule confirmed.

So one marina on this river just reopened with a name attached and a CEO quote. The other is still waiting on federal sign-off for a bigger version of itself. If you're hoping to dock downtown, which project you're tracking changes what you should expect this year.

The Plan for the Space Between Them

The city's separate ambition is called the Innovation Walk, a mile-long redesign of the public riverfront running roughly from Hendry Street to the Edison and Ford Winter Estates. It would touch Centennial Park, the eight-acre green space that already anchors the downtown waterfront with its inclusive playground and the All Veterans Memorial. Seven urban planning firms competed for the job last fall, and in November 2025 the city's review committee recommended Perkins&Will to lead the design.

In late August 2026, that design team previewed its concept to the city's review board. Board members asked practical questions: whether two-way traffic would stay on West First Street, how existing driveway cuts would be handled, where on-street parking would survive, and how a proposed floating boardwalk would get permitted, since waterfront structures like that typically require Army Corps of Engineers involvement. The design team said the current concept keeps two-way traffic and anticipated further coordination with both city staff and private property owners.

At that meeting, Legacy Harbour Marina's attorney said the marina was nearing completion of its broader redevelopment and had a pending permit of its own. She said the proposed drawbridge and boardwalk alignment could affect that timeline and requested further conversations with private waterfront owners before the design is finalized.

The public path along this stretch of river remains a concept, and further coordination with private property owners is part of the design process.

What This Actually Changes This Fall

If you already boat out of Legacy Harbour or you've been watching for its reopening, that part is real and it happened. Slip requests are being taken through the marina's own site and through Dockwa, with formal reservations launching once a firm date is confirmed for full capacity.

If you're hoping for a slip at the city's Yacht Basin near the Edison Bridge, that timeline still runs through federal permitting rather than local construction, and nothing in the public record points to a near-term opening.

If you like walking the river path through Centennial Park, nothing about your route changes this year. The Innovation Walk is a concept under negotiation, not a construction project with a start date. The concerns raised in August are exactly the kind of details that get worked out, sometimes for months, before a shovel goes in the ground.

And if you've heard about the two 25-story towers planned as part of Legacy Harbour's full master plan, 377 entitled units with Michael Graves Architecture and Design attached as the architect, that piece is even further out. The city approved the density last year, but ownership still needs a development partner, and the land-use attorney representing the project has said tower construction is unlikely within the next two years. The marina and the restaurant are the visible, near-term change. The skyline isn't the story yet.

The marina's reopening and the Innovation Walk's design process are unfolding on separate timelines. Legacy Harbour spent four years and $15 million rebuilding docks after Ian, while the city continues developing its public riverfront concept. The marina's attorney requested further conversations with private waterfront owners before the design is finalized. Together, these projects show how private investment and public planning are shaping this stretch of river.

If you're weighing what any of this means for a home near the river, or you just want a straight read on which projects are real and which are still concepts, KE Group is happy to walk through it with you.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.

Leaving Nothing on the Table

Every detail matters. From strategic pricing and tailored marketing to skilled negotiation, we're committed to maximizing your property's value and ensuring no opportunity is overlooked.

Let's Connect