Pelican Landing's Beach Season Opens on a Waterfront Mid-Rebuild

This summer, after the thatched roof went on the new shade pavilion at the Big Hickory Island dock, the crew dragged a magnet across the sand to pick up any nails or screws dropped during construction. It's a small cleanup step on a structure that is built to withstand hurricane-force winds. It also points to where the community's waterfront work stands this fall.

For most of the last two years, work at the Beach Park and the Coconut Road marina meant restoring what the 2024 storms had taken. That phase is largely finished. What comes next is a rebuild: a new dock, a planned marina building, and shoreline work. Each of those runs on a permit review or a design process, which makes for a longer and less predictable calendar than the repair phase had.

How the Repair Phase Played Out

According to the Pelican Landing Community Association's own year-end recap in Landing Life, the recovery came in this order:

  1. Marina docks and seawall. Repairs to the marina and reconstruction of its docks were completed earlier, and the seawall and sea cap needed major work. Kayaking and sailing reopened at the marina once that was done.
  2. The Beach Park. The island park reopened on Feb. 13, 2025, after a tropical storm and two hurricanes in 2024. The PLCA reported thousands of residents and guests visited after the reopening.
  3. Marina landscaping. New plantings went in around the marina, which the association said had been without greenery since Hurricane Ian.
  4. The Coconut Road parking lot. In mid-October 2025 the lot was milled and resurfaced, the bumpers were repainted, and landscaping was added around the edges.
  5. Redfish Docks. The docks behind the Butterfly Garden were destroyed by Hurricanes Helene and Milton. They were rebuilt at a higher elevation, and the PLCA's spring update said they would soon reopen. That newsletter also mentions that manatees are often spotted there.

Every item on that list put back something that already existed. The Redfish Docks show a small change in approach, though. They were rebuilt to sit higher than before. As of the September 2026 issue, they're available to lease for flat skiffs or pontoon boats, and personal watercraft are not permitted. Jamie Boese, Director of Island and Marina Operations, is the contact for lease questions, along with the marina office.

The First New Addition Is on the Island

The Chikee Hut at the island dock is the first part of this cycle that adds something new to the island rather than restoring it. The Native American Chikee Huts team built it this summer. The team is made up of members of the Seminole tribe, and it also designed and built two picnic and barbecue huts on the beach. Its purpose is simple. It shades people waiting for the boat back to the mainland, a spot where the 34-acre island had offered little cover.

The construction followed traditional methods. The frame is pressure-treated southern pine. Individual palm fronds were taken to the marina, loaded onto barges and carried across to the island. Each frond was then nailed through the stem to the frame above. When the September issue went to print, benches for people waiting on the boat were still being built.

The Chikee Hut is not a lightning shelter. The PLCA's instruction is to go to the main pavilion when the lightning siren sounds. On a summer afternoon when a storm builds over Estero Bay during the 12-minute crossing, the shaded spot by the dock and the safe spot are in different places.

The hut was finished quickly once permits were in hand. In the April/May issue, chickee construction was still "in the final stages of the permitting process." By September it was standing on the island. That same spring update set out a second summer project that has not moved as fast.

Where the Rebuild Stands This Fall

In spring, the association planned to repair seven of the eight groins along the shoreline over the summer and to run a beach sand nourishment project in sections so the Beach Park could stay open. The September update from Boese describes the association as "currently awaiting reviews from regulatory agencies regarding beach sand nourishment, dredging and the island's water system." Unless the PLCA announces otherwise, residents heading out to the island this season should assume nourishment is still pending.

Here is where each piece stood as of the September 2026 Landing Life:

Project Status as of September 2026 What it is waiting on
Chikee Hut and beach picnic huts Built this summer Benches still being added
Redfish Docks at Spring Creek Rebuilt higher, open for lease Nothing; flat skiffs and pontoons only
South Dock Construction set to begin in September Construction underway or about to start
Marina building Conceptual floor plan in development Design work
Beach sand nourishment Planned for summer, not yet confirmed Regulatory review
Dredging Under review Regulatory review
Island water system Under review Regulatory review

The marina building has the longest history. The association described "many years of discussions and inquiries" before the Lee County Board of County Commissioners approved vacating an easement on the portion of Coconut Road that the PLCA owns. The year-end recap said that milestone "paves the way for rebuilding the Marina." Nine months later, the building is at the concept stage. No cost or construction schedule has been published in the newsletter so far.

The Same Shift Is Happening on the Roads

The waterfront isn't the only place the work has grown from a spot fix into a larger plan. The PLCA's new community infrastructure project started with repairs in a small area of Goldcrest Drive. It now covers the whole community, including a review of all 69 miles of roadway and about 8.5 miles of sidewalk. Omega Consulting Group identified about 150 areas needing repair or maintenance, covering sidewalks, roadways, drainage structures, curbing and pavers. After a bidding process, Onyx Asphalt was selected and began work at the north end of Goldcrest Drive. Expect flaggers who may stop or direct traffic around the crew's equipment. The association says it will post updates on affected streets as the work moves along.

Planning Beach Days This Season

The rebuild doesn't close the island. The Beach Park page describes it as available 364 days a year. A fall 2026 shuttle timetable has not been published in the newsletter yet, so last season's pattern is the best guide until the PLCA posts the new one. In February 2026, two boats ran at the top and bottom of the hour. On designated extended-hours days, the park stayed open until sunset, umbrellas came off the beach at 4:20 p.m., and boats ran every 30 minutes until about an hour before sunset. Those extended dates ran through mid-April, so check with the association before planning a late-afternoon trip this fall.

A few rules and dates to keep handy:

  • Guests. Every guest needs a valid guest pass for any PLCA amenity. No one guest can accumulate more than 30 days of access in a calendar year, and an owner or tenant can request up to eight concurrent passes per unit. Emailed QR codes work only on the dates listed.
  • Sailing. Last season, certification lessons ran Monday through Thursday at 9 a.m., 11 a.m., 1 p.m. and 3 p.m. The association's sailing page lists complimentary lessons.
  • Oct. 29, 2026. The PLCA Budget Adoption Meeting.
  • Dec. 1 and Jan. 1. The annual assessment is mailed by Dec. 1 and due by Jan. 1.
  • March 27, 2027. The Annual Member Meeting.

The next schedule changes on the island will come from agency decisions on nourishment, dredging and the water system, and the PLCA reports that news first in Landing Life.

If you're weighing a Redfish Docks lease, wondering how the Coconut Road marina rebuild might affect your boating, or thinking about how these amenity changes affect the value of a home in Pelican Landing, KE Group is glad to talk it through with you. Let's Connect.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.